1. Write down the decision the test supports
Examples include approving a launch, assessing peak-traffic readiness, comparing a release with a baseline, or investigating a slow API operation. State the system boundaries and what the result must prove. A test of a health endpoint cannot establish checkout capacity.
2. Identify critical journeys and representative data
Use production analytics or documented assumptions to choose the operation mix. Include authentication, reads and writes, payload sizes, cache behavior, and relevant dependencies. Keep test data representative but non-sensitive, and confirm that repeated writes do not unintentionally exhaust or corrupt the dataset.
3. Choose a traffic model deliberately
Concurrent users and requests per second are not interchangeable. In a closed workload, users generally wait for a response before continuing, so slower responses can reduce request rate. An arrival-driven workload schedules demand independently; it still requires enough generator capacity to sustain that schedule.
Define arrival patterns, pacing, journey mix, warm-up, stage duration, and recovery periods. Record both intended and achieved load. For LPS configuration concepts, see rounds and iteration modes; confirm the chosen configuration models the intended behavior.
4. Select load, stress, spike, or endurance testing
- Load: evaluate representative expected demand.
- Stress: observe degradation beyond expected demand, within authorized boundaries.
- Spike: assess rapid demand changes and recovery.
- Endurance: investigate behavior over sustained operation.
Choose the combination that addresses your risk. A short high-load test does not replace an endurance assessment, and a stress result is not automatically a production capacity limit.
5. Agree measurable acceptance criteria
Define response-time percentiles, error definitions, throughput requirements, and any resource or recovery conditions per important operation. Specify whether latency excludes failed requests and how timeouts are counted. Avoid using average latency alone.
Illustrative criterion, not a default: an agreed workload might require successful-response p95 at or below 500 ms and failures at or below 1% during its steady target stage. Real targets must come from your product expectations and service objectives.
6. Establish safe execution boundaries
Only test systems you own or have explicit permission from the system owner to test. Using LPS does not grant permission to test any system. Agree traffic limits, monitoring, stop conditions, test windows, and recovery responsibilities with the system owner. Do not load-test payment providers, email services, or other third parties without their permission. Use an appropriate staging environment where possible, and document differences from production.
7. Validate before scaling
Run a low-load check. Confirm successful authentication, correct payloads, expected response content, realistic data distribution, and the intended journey sequence. A fast validation failure is not a fast successful transaction.
Check generator CPU, memory, network, connection behavior, and scheduling. If achieved load falls below intended load, investigate the test setup before attributing a capacity limit to the application.
8. Collect evidence and preserve context
Correlate request outcomes with application traces, dependency metrics, and infrastructure behavior over matching time windows. Record configuration, tool version, environment, dataset, timestamps, and raw results or agreed exports.
Separate observations from hypotheses. High latency alone does not prove a database bottleneck. Identify the additional measurement or controlled experiment that could confirm a suspected cause.
9. Turn findings into a repeatable next step
Explain which criteria were met, which were not, and what the evidence cannot establish. Prioritize follow-up work by business impact and confidence. When comparing a change, repeat the same relevant workload and account for environment differences and normal run-to-run variation.
See the synthetic sample performance report for an example of transparent reporting, including its limitations.
A compact pre-run checklist
- Decision, system scope, and explicit test authorization agreed.
- Journey mix, data, authentication, and traffic assumptions documented.
- Success criteria, failure definitions, and safety stop conditions established.
- Environment differences and third-party boundaries recorded.
- Low-load validation and load-generator headroom checked.
- Monitoring, result storage, and handover responsibilities ready.